3 kW on-grid systems are a great way for homeowners to save on their electricity bills. Before switching your system on however you will need to carry out some checks to ensure all important components of the system have been correctly fitted.
Commissioning checks ensure that the whole solar system is safe and fully connected to ensure that everything works correctly. This includes ensuring there are no wiring errors, incorrect voltages and poor earthing.
Understanding how commissioning checks should be carried out is an important part of fitting an enPrimo 3 kw Solar Inverter or residential solar system. This ensures that there are no unnecessary faults and the system will work reliably.
1. Inverter Fitting
First we need to ensure that the inverter has been fitted correctly. The unit should be installed as per the manufacturer’s instructions securely to a suitable wall.
Ensure that the inverter has sufficient ventilation space to allow heat to dissipate from the unit. Avoid placing this equipment in direct contact with rain water, high humidity, high dirt and heat unless you have equipment that is rated to work in these environments.
Before you commission your unit ensure that:
The unit has been fitted securely and has been fitted correctly.
There is enough room for ventilation.
There are no obvious signs of damage on the unit.
Cables have been fitted securely.
You can safely access the unit.
If the enPrimo 3kW has been fitted correctly following the fitting guidelines then you will find it easier to access the unit.
2. Solar Panel and DC Checks
Solar panels produce DC electricity which needs to be converted to AC by the inverter. If you have incorrect wiring then this could impact performance and damage your inverter.
Before you connect your solar strings to your unit, your installer should ensure that the layout of your system is correct and matches the design. The number of panels per string should be within the allowed DC limits.
Ensure that:
Polarity has been fitted correctly (positive and negative connections).
Open Circuit Voltage has been checked.
Voltage readings are correct for the panels you have fitted.
DC cables and connections show no signs of damage.
Insulation resistance test has been carried out.
Always ensure that the configuration of your panels matches the inverter input requirements.
This ensures that the solar array will supply your inverter safely.
3. AC Connection Checks
As on-grid inverters work with the grid you will need to ensure that your AC connections are correct.
Check that the AC cables, terminals, circuit breaker and isolator are suitable for your system design. Cable sizes should be suitable for the current, length of cable, installation and electrical requirements.
Ensure that:
Connections are correct (line, neutral and earth if applicable).
AC cables are in good condition and have been terminated correctly.
Circuit protection and isolation is suitable.
Grid voltage and frequency is correct.
Connections are secure and there are no exposed cables or damaged insulation.
Ensure that the grid supply is within the allowed limits of your inverter and local requirements. If the voltage or frequency is not within specification then this should be investigated before powering up.
Having correct AC wiring will ensure that your enPrimo 3kW works safely and will reduce nuisance trips.
4. Earthling and Protection
One of the most important checks you can carry out before commissioning your solar installation is to ensure that your earthing has been done correctly. Having a correctly designed earthing and bonding system will help protect you from electric shocks.
Ensure that earthing connections have been made on your inverter, solar panel mounting and any exposed conductive parts. This should be done as per the approved design and standards.
Where necessary surge protection should also be checked.
Ensure that:
Protective earth has been made.
Earth resistance has been measured.
Protection components have been checked and indicators are showing.
AC and DC isolation points are accessible and labelled.
All warning labels have been added.
Earthing should be done in accordance with the relevant regulations and project specifications. If any of your safety checks fail then you should rectify the problem before commissioning.
5. Inverter Compatibility
Before turning your system on you should ensure that your inverter is compatible with your solar array and electrical supply.
Your installer should ensure that the model, rated power, DC input limits, MPPT and grid parameters match the approved design. Your solar panels should be suitable for the inverter input.
Ensure that you are using the correct datasheet and installation manual for the model of inverter you are installing. This will ensure that you are using the correct operating limits and configuration. Do not use settings from a different model of inverter.
Depending on your installation you may need to:
Select the correct country/grid profile.
Ensure voltage and frequency protection is set correctly.
Set monitoring.
Set export control if needed.
Check date/time and relevant parameters.
Incorrect settings can cause nuisance trips or stop the inverter from connecting to the grid. All settings must be carried out in accordance with manufacturer’s instructions and local electricity distribution requirements.
6. Grid Synchronisation and Anti-Islanding
On-grid inverters depend on the grid to work. Normally they will stop providing power if there is no grid supply.
This is known as anti-islanding.
Qualified personnel should ensure that your inverter will work correctly with the grid protection and anti-islanding features. This can be done by following the manufacturers instructions.
Ensure that:
The inverter will only connect if it detects an acceptable grid supply.
Synchronisation has been set up correctly.
Voltage and frequency are within acceptable limits.
The inverter will disconnect correctly if conditions are not acceptable.
The system will not continue to supply power to the grid.
Always carry out these tests using approved methods. Never attempt to test anti-islanding by carrying out unsafe live work.
Correctly verifying these will ensure that your inverter will work as intended and protect anyone working on your electrical network.
7. Monitoring
Once all electrical and safety checks have been carried out your installer can follow their approved start-up procedure. Once started you should monitor the system to ensure that your inverter is working correctly and no faults are reported.
Check that your inverter is displaying the correct information. This includes inverter status, DC voltage, AC supply, grid status and any alarms.
Ensure that:
Inverter status shows it is working correctly.
Solar generation readings match actual conditions.
AC is being supplied when there is enough sun and acceptable grid conditions.
Monitoring is working and showing updated data.
Any warnings are investigated.
Take note of your initial readings so you can compare them to future performance.
8. Documentation and Handover
Commissioning should finish with documentation and handing over to your homeowner. This is often forgotten but will help them understand how the system works and make it easier for them in the future.
Your installer should provide information on the equipment, test results, operating instructions and warranty details.
Ensure that:
Inverter model and serial number.
Solar panel and string configuration.
DC and AC test results.
Earthing and protection checks.
Monitoring details.
Instructions on how to shut down and recommendations for maintenance.
Warranty documents and contact details.
Your homeowner should understand that normally on-grid systems will not provide any backup power during a power cut. You would need a system specifically designed for this.
Conclusion
Commissioning is an important part of ensuring your 3 kW on-grid system works safely. By ensuring that your inverter has been fitted correctly, DC connections are correct, earthing has been done, grid synchronisation and monitoring has been carried out you can be sure that your installation will work correctly.
Whilst choosing the correct equipment is important, having it fitted and tested correctly is equally important. The enPrimo 3kW can be used for residential applications as long as the specifications match your requirements. Following the manufacturers instructions and carrying out all commissioning checks will help your installer identify any problems and give your homeowner more confidence in their investment.
Ensure that all electrical tests have been passed, you have the correct approvals and your installation meets the relevant safety standards before declaring any systems ready.
FAQs
1. What is commissioning?
Commissioning involves checking, testing and setting up your solar panels, inverter, wiring, earthing and grid connections.
2. Why do I need to check the DC polarity before switching my EnPrimo 3kW on?
Correct polarity will ensure that the positive and negative cables are connected to the correct terminal. If they are connected incorrectly this may cause faults and damage equipment.
3. Will my on-grid residential inverter work during a power cut?
Normally no. On-grid inverters will switch off if there is no grid supply. In order to have backup power you would require a system designed for this.
4. My 3kW inverter will not start what should I do?
A qualified installer should check that there is grid supply, correct DC voltage, polarity, AC connections, protection settings and any error codes displayed. Follow the manufacturers troubleshooting guide.
5. Who should commission my residential solar inverter?
Qualified personnel should commission your inverter. They should know the manufacturers procedures and electrical safety requirements.